Willavale Park
About the project
X-ELIO is proposing to build a battery energy storage system (BESS) in Wollogorang, NSW.
The site has been chosen due to its proximity to existing transmission lines, which minimises the length of the transmission route and makes it easier to store excess energy for the national grid.
Following X-ELIO’s submission of its Scoping Report, the Department of Planning, Housing and Industry (DPHI) issued the Secretary’s Environmental Assessment Requirements (SEARs) for the Project in December 2024. We are continuing studies to assess key technical, environmental, and social features to inform the preparation of the Environmental Impact Statement (EIS) Report.
The project team is committed to engaging with the community throughout the life of the project and leaving a positive long-term impact on the region.
Project footprint
The preliminary footprint for the proposed Willavale Park BESS is shown to the right. Comprehensive environmental assessments and habitat and biodiversity studies are currently being undertaken as part of the planning process and to inform the exact site layout.

Project timeline
This project will follow the standard State Significant Development Application (SSDA) process, which will be submitted to the NSW Department of Planning, Housing and Infrastructure (DPHI) for assessment.
The final development footprint will be provided in the Environmental Impact Statement (EIS) and will include feedback obtained through community and stakeholder consultation.
We anticipate lodging the EIS Report to the NSW Government in Q4 2025.
Latest Updates
More information is provided in the latest Project Update
Community engagement
The community will have further opportunities to learn about our plans and provide feedback throughout the planning and permitting process. X-ELIO is committed to working with our neighbours and the wider community and will continue to provide updates as we have more information.
Have your say
We will be in Goulburn town centre on Friday 11 and Saturday 12 April 2025 to provide information and listen to feedback on our other local project, the Willavale Park BESS. We would like to hear from as many community voices as possible, so please come and see us at the following times and locations:
• Friday 11 April | 3:00PM – 7:00PM
• 12-20 Verner Street, Goulburn
• Saturday 12 April 2025 | 08:30AM – 12:30PM
• Opposite the public toilets close to 3 Montague Street, Goulburn
FAQs
Local benefits and jobs
We are working with Goulburn Mulwaree Council and other relevant local organisations to understand how we can support local businesses, groups, and nearby communities during the construction and operations of the two projects.
As we develop these Projects, we welcome your suggestions.
Guiding our planning is X-ELIO’s Community Plans, which outline four community pillars:
- Education – actions that cover education development at all levels.
- Environment – actions that focus on the preservation and improvement of the ecosystem.
- Health – actions to achieve an eco-friendly life in the community.
- Communities – actions that target a healthy lifestyle and humanitarian aid.
Construction requires a variety of roles such as civil contractors, tradespeople and electricians.
Once operational, each project will be largely run by four to five people based onsite.
We are also looking for opportunities to collaborate with local training providers to upskill the local workforce to enhance relevant industry qualifications.
The procurement process will likely begin seven to eight months before construction starts. Local businesses can indicate their interest in being involved in the project/s via the project email addresses;
Purpose of a Battery Energy Storage System
Storing energy provides greater flexibility and reliability in power generation by helping to match the generation of renewable energy with energy consumption.
This helps to stabilise the grid by managing peaks in supply and demand and can provide backup power in case of an outage.
Willavale and Canyonleigh batteries will absorb energy directly from the national grid during times of low demand (i.e., in the middle of the day or night) and store the excess electricity. During periods of higher power demand (such as in the evenings), the battery will feed electricity back into the grid.
Connection between projects
Project footprints
Project approvals
X-ELIO submitted a Scoping Report to the NSW Department of Planning, Housing and Infrastructure (DPHI) in late 2024, which included the results of site investigations, early consultations and initial studies in the area.
DPHI issued the Secretary’s Environmental Assessment Requirements (SEARs) for the Project on 12 December 2024. These specify what issues are required to be addressed in the Environmental Impact Statement (EIS), which is the current stage of the review process.
The EIS assesses the potential environmental, cultural heritage, community, social and economic impacts of the project during the construction, long-term operation, and decommissioning phases.
X-ELIO is using the SEARs to guide it through the EIS process to better understand any impacts the Project may have on the surrounding areas. As we do this, we’ll continue to communicate with landowners, adjacent communities and other stakeholders.
Secretary’s Environmental Assessment Requirements (SEARs)
- Traffic and transport
- Noise during construction and operations
- Biodiversity
- Visual & landscape impacts
- Indigenous and historic heritage
- Electromagnetic interference (EMI)
- Bushfire prevention and management
- Waste management
- Socio-economic factors
- Water use and management
Fire risks
Management measures implemented will be consistent with requirements of the NSW Government and the NSW Rural Fire Service (RFS) Planning for Bush Fire Protection guidelines.
X-ELIO is committed to working with the Goulburn Mulwaree Rural Fire District to understand site-specific requirements and firefighting access.
Appropriate site-specific mitigation measures such as Asset Protection Zones, adequate water supply and perimeter roads will be incorporated into the project design and agreed upon with the Rural Fire District prior to construction.
Noise during operations
Notwithstanding the advice in this section and visual amenity (below), the Project Area is situated away from a large number of sensitive receptors, such as residential areas, thereby reducing the likelihood of adverse amenity impacts, such as noise, dust or visual disturbance.
As part of the EIS, we will undertake a noise impact assessment to model the predicted noise levels both during construction, and when the BESS is operational. The assessment will be based on the specific construction and operational equipment to be used across both stages.
If required, project designs will consider mitigation measures such as the installation of noise barriers or control the cooling system fans speed.
Operational noise impacts will be assessed in line with the NSW Environment Protection Authority’s (EPA’s) NSW Noise Policy for Industry.
Noise and dust during construction
If required, we will use construction mitigation measures, such as installing temporary noise barriers.
The Department will also stipulate acceptable noise levels if it approves the Project.
Visual amenity
Once this has been undertaken, we will talk with nearby residents to understand the specific needs of neighbours based on visual impacts for nearby occupied dwellings so that appropriate mitigation measures can be determined and incorporated into the project design.
Road and traffic impacts
Prior to the construction phase, using traffic modelling we will work closely with Council and regulators to manage potential impacts to local roads associated with the project.
Additionally, we will provide community with notification before any activities that may cause traffic impacts, before any access changes, or if we think there might be delays to travel times caused by construction works. Traffic management plan will also support this.
Project lifespan
Decommissioning and future land use
As part of the permitting process, a detailed decommissioning plan will be created for the project. This plan includes a commitment and a budget to implement and specifications as to how the site will be returned to its original condition.
X-ELIO welcomes information from the local community regarding agricultural land use, as it will help us better understand potential past, present, and future agricultural impacts and mitigation measures.
Location
- Land suitability and environmental factors such as topography, soil and hydrology.
- Proximity to grid infrastructure and network load capacity.
- Existence of transmission lines within the site footprint.
- Site accessibility via road.
The location has been chosen due to the proximity of a transmission line corridor, making it easier to connect energy to the grid.
Project timelines
We continue our technical studies and planning for engagement activities to seek input from the community to inform the project design. This will feed into the EIS Report, which we hope to submit to DPHI in late 2025. We can only establish timing for when construction might start if and when approval is provided from DPHI.
Project details
The battery energy storage systems will collect energy from the grid and store it, in order to release it back into the grid when its needed.
Road set back
Biodiversity values
Comprehensive environmental assessments, including habitat and biodiversity studies will be undertaken as part of the Environmental Impact Statement process to help avoid or mitigate any environmental impacts associated with the Project.