Canyonleigh
About the project
X-ELIO is proposing to build a Battery Energy Storage System (BESS) in Brayton, NSW.
The site has been chosen due to its proximity to the existing Marulan Substation and proposed new power station, which minimises the length of the transmission route and makes it easier to store excess energy for the national grid.
Following X-ELIO’s submission of its Scoping Report, the Department of Planning, Housing and Industry (DPHI) issued the Secretary’s Environmental Assessment Requirements (SEARs) for the Project in December 2024. We are continuing studies to assess key technical, environmental, and social features to inform the preparation of the Environmental Impact Statement (EIS) Report.
The project team is committed to engaging with the community throughout the project’s life and leaving a positive long-term impact on the region.
Project footprint
The preliminary footprint for the proposed Canyonleigh Project is shown to the right. Comprehensive environmental assessments and habitat and biodiversity studies are currently being undertaken as part of the planning process and to inform the exact site layout.

Project timeline
This project will follow the standard State Significant Development Application (SSDA) process, which will be submitted to the NSW Department of Planning, Housing and Infrastructure (DPHI) for assessment.
The final development footprint will be provided in the Environmental Impact Statement (EIS) and will include feedback obtained through community and stakeholder consultation.
We anticipate lodging the EIS Report to the NSW Government in Q4 2025.
Latest Updates
More information is provided in the latest Project Update
Community engagement
The community will have further opportunities to learn about our plans and provide feedback throughout the planning and permitting process. X-ELIO is committed to working with our neighbours and the wider community and will continue to provide updates as we have more information.
Have your say
Email Update: We’re aware that some individuals may have experienced difficulties reaching the team due to an email address error. For future reference, the correct email to use for this proposed project is canyonleigh.community@x-elio.com
FAQs
Local benefits and jobs
We are working with Goulburn Mulwaree Council and other relevant local organisations to understand how we can support local businesses, groups, and nearby communities during the construction and operations of the two projects.
As we develop these Projects, we welcome your suggestions.
Guiding our planning is X-ELIO’s Community Plans, which outline four community pillars:
- Education – actions that cover education development at all levels.
- Environment – actions that focus on the preservation and improvement of the ecosystem.
- Health– actions to achieve an eco-friendly life in the community.
- Communities – actions that target a healthy lifestyle and humanitarian aid.
Each project’s construction phase typically takes between 12 and 18 months and each site is expected to need 200 to 300 people during construction, with peak activity occurring about halfway through construction.
Construction requires a variety of roles such as civil contractors, tradespeople and electricians.
Once operational, each project will be largely run by four to five people based onsite.
Additionally, many indirect jobs will be generated in hospitality, accommodation, and general services.
We are also looking for opportunities to collaborate with local training providers to upskill the local workforce to enhance relevant industry qualifications.
X-ELIO has an existing procurement team in Australia, and the construction team is expanding.
The procurement process will likely begin seven to eight months before construction starts. Local businesses can indicate their interest in being involved in the project/s via the project email addresses;
Purpose of a Battery Energy Storage System
Storing energy provides greater flexibility and reliability in power generation by helping to match the generation of energy with energy consumption. This helps to stabilise the grid by managing peaks in supply and demand and can provide backup power in case of an outage.
Willavale and Canyonleigh batteries will absorb energy directly from the national grid during times of low demand (e.g., in the middle of the day or night) and store the excess electricity. During periods of higher power demand (e.g., evenings), the battery will feed electricity back into the grid.
Local battery energy storage systems for use locally
Financials
Connection between projects
Project footprints
Project approvals
X-ELIO submitted a Scoping Report to the NSW Department of Planning, Housing and Infrastructure (DPHI) in late 2024. The report included the results of site investigations, early consultations, and initial studies in the area.
DPHI issued the Secretary’s Environmental Assessment Requirements (SEARs) for the Project on 12 December 2024. These specify what issues must be addressed in the Environmental Impact Statement (EIS), which is the current stage of the review process.
The EIS assesses the project’s potential environmental, cultural heritage, community, social and economic impacts during the construction, long-term operation, and decommissioning phases.
X-ELIO is using the SEARs to guide it through the EIS process to understand better any impacts the Project may have on the surrounding areas. As we do this, we’ll continue communicating with landowners, adjacent communities and other stakeholders.
Secretary’s Environmental Assessment Requirements (SEARs)
- Traffic and transport
- Noise during construction and operations
- Biodiversity
- Visual & landscape impacts
- Indigenous and historic heritage
- Electromagnetic interference (EMI)
- Bushfire prevention and management
- Waste management
- Socio-economic factors
- Water use and management
Fire risks
The batteries are proposed to be stored in purpose-built containers, both of which undergo rigorous fire testing as part of the manufacturing process. Additionally, each container has its own gas-based fire suppression system that activates in the unlikely event of a fire incident. The gas replaces the oxygen in the container, so the fire goes out. Cooling pads are also placed between the battery cells and other components to enhance thermal conductivity, preventing overheating and ensuring efficient operation.
Other mitigations include creating a gravel platform for the battery containers to sit on and creating robust weed management programs to ensure no fuel is near the infrastructure, so it isolates the BESS.
X-ELIO is exploring several other mitigations, including working with the Rural Fire Service (RFS) to deliver firefighting training to its operational staff and housing additional firefighting equipment on site or nearby. Equipment might also be shared with local RFS teams to assist with any regional fire incidents.
The management measures implemented will be consistent with the requirements of the NSW Government and the NSW Rural Fire Service (RFS) Planning for Bush Fire Protection guidelines.
X-ELIO is committed to working with the Goulburn Mulwaree Rural Fire District to understand site-specific requirements and firefighting access. For example, a second access road has been added to ensure alignment with good practice.
Appropriate site-specific mitigation measures such as Asset Protection Zones, adequate water supply and perimeter roads will be incorporated into the project design and agreed upon with the Rural Fire District before construction.
Noise during operations
Notwithstanding the advice in this section and visual amenity (below), the Project Area is situated away from a large number of sensitive receptors, such as residential areas, thereby reducing the likelihood of adverse amenity impacts, such as noise, dust or visual disturbance.
As part of the EIS, we will undertake a noise impact assessment to model the predicted noise levels during construction and when the BESS is operational. The assessment will be based on the specific construction and operational equipment used across both stages.
If required, project designs will consider mitigation measures such as installing noise barriers or controlling the speed of the cooling system fans.
Operational noise impacts will be assessed in line with the NSW Environment Protection Authority’s (EPA’s) NSW Noise Policy for Industry.
Noise, vibration and dust during construction
Notwithstanding the advice in this section and the visual amenity (below), the Project Area is situated away from many sensitive receptors, such as residential areas, thereby reducing the likelihood of adverse amenity impacts, such as noise, dust, or visual disturbance.
We will use construction mitigation measures, such as installing temporary noise barriers if required.
The Department will also stipulate acceptable noise levels if it approves the Project.
Visual amenity
Once this has been undertaken, we will talk with nearby residents to understand the specific needs of neighbours based on visual impacts for nearby occupied dwellings so that appropriate mitigation measures can be determined and incorporated into the project design.
Road and traffic impacts
Prior to the construction phase, we will work closely with the Council and regulators and use traffic modelling to manage potential impacts on local roads associated with the project.
In addition, projects of this type usually require dilapidation surveys to be completed before and after construction, and the project developer must bring the road back to its original quality at project completion.
The proposed Project site at Canyonleigh is accessed via Canyonleigh Road, an unsealed local road. If the project is approved, X-ELIO will work with the Council and project developers in the area (as we will likely share haulage routes) to monitor or maintain the road.
At Willavale, project access may be required via Wollogorang Road, which is unsealed. Should it be required for construction haulage, X-ELIO will work with NSW DPHI on requirements to upgrade or maintain the road.
Additionally, we will notify the community before any activities that may cause traffic impacts, before any access changes, or if we think there might be delays to travel times caused by construction works. The traffic management plan will also support this.
Project lifespan
Decommissioning
A detailed decommissioning plan will be created for the project as part of the permitting process. This plan includes a commitment and budget to implement it and specifications for how the site will be returned to its original condition.
X-ELIO welcomes information from the local community regarding agricultural land use, as it will help us better understand potential past, present, and future agricultural impacts and mitigation measures.
Location
- Land suitability and environmental factors such as topography, soil and hydrology.
- Proximity to grid infrastructure and network load capacity.
- Site accessibility via road.
Additionally, the site’s proximity to Transgrid’s Marulan Substation was a key factor in site selection, minimising the length of the transmission route and making it easier to store power from and provide power back to the national grid.
Project timelines
Currently, we are continuing our technical studies and planning engagement activities to seek input to inform the project design. This will feed into the EIS Report, which we hope to submit to DPHI in late 2025. We can only establish when construction might start if approval is provided from DPHI. It is expected to start in in early 2026.
Project details
The battery storage capacity is 300 MW, which allows for up to 4 hours of storage.
Road set back
